DENVER (AP) - A natural gas-fired power plant in Lamar that was converted to run on coal would go on standby under a proposed settlement with WildEarth Guardians, which alleged Clean Air Act violations at the plant.

According to a consent decree, the Arkansas River Power Authority and the city-owned utility Lamar Light and Power also agreed to pay $125,000 for a clean energy project in southeast Colorado, plus $325,000 for plaintiffs' legal costs.

They agreed not to run the 44-megawatt plant, except for limited testing, until Feb. 1, 2022. They would have to pay $125,000 more if they don't secure long-term contracts by 2019 for power beyond Feb. 1, 2022.

WildEarth Guardians says it's cheaper to buy power elsewhere than to run the plant.

A federal judge must approve the deal.

(© Copyright 2013 The Associated Press. All Rights Reserved. This material may not be published, broadcast, rewritten or redistributed.)

View CBS News In
CBS News App Open
Chrome Safari Continue
Be the first to know
Get browser notifications for breaking news, live events, and exclusive reporting.