Repair Work Begins On Tennessee Pass Sinkhole

LEADVILLE, Colo. (AP) — Repair work is starting on a 100-foot-deep hole beside U.S. 24 on Tennessee Pass.

The hole opened July 9 when the soil gave way above an abandoned, collapsed railroad tunnel.

Hayward Baker Inc. won a roughly $830,000 contract to do repairs. Work was getting under way Wednesday.

The repair job will close a four-mile stretch of U.S. 24. The Colorado Department of Transportation hopes to reopen at least part of the highway by Aug. 6. The USA Pro Challenge cycling race plans to use the route Aug. 23.

CDOT says Hayward Baker will receive a $5,000 incentive per day for an early opening. They will be assessed $5,000 each day they are late.

CDOT says the total cost of repairs, including traffic control, is estimated to be $1.5 million.

(© Copyright 2012 The Associated Press. All Rights Reserved. This material may not be published, broadcast, rewritten or redistributed.)

Comments

Leave a Reply

Please log in using one of these methods to post your comment:

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

More From CBS Denver

Enter To Win!
Weather App

Listen Live

AM/FM Stations

Featured Shows & Multimedia